El Kureimat III 750 MW Combined Cycle Power Plant Steam Turbine Generator & Auxiliaries
15/05/2007
The ALSTOM-led consortium formed by ALSTOM Power Generation AG (Germany), ALSTOM Egypt for Power & Transport Projects SAE and INITEC Energia S.A. (Spain) has been awarded a 48.5 million Euros contract for the supply and installation of a 250 MW Steam Turbine Generator & Auxiliaries for El Kureimat III 750 MW Combined Cycle Power Plant.

The contract was signed on 15/05/2007 in the presence of Minister of Electricity & Energy, Dr. Hassan Younes; Chairman of the Egyptian Electricity Holding Company "EEHC", Dr. Mohamed Awad and Chairman of the Upper Egypt Electricity Production Company, Eng. Shaaban KHALAF.

This is the third 250 MW Steam Turbine and Auxiliaries package awarded to the same consortium. Same packages were awarded in 10/2004 for Cairo North II 750 MW and in 05/2005 for New Talkha 750 MW Combined Cycle Power Plants. This consortium has also been awarded in 01/2007 the contract for 2 x 350 MW steam turbine generator units & condensers for El Tebbin Thermal Power Plant in Cairo.

This project is in the framework of the Electricity Sector's current five year fast-track program 2007-2012 to add 7800 MW to the installed capacity, serving industrial development and satisfying increasing household demand on electricity.

El Kureimat is located 95 K M south Cairo on the eastern bank of Nile river, in the zone administered by Upper Egypt Electricity Production Co. By the completion of all of its modules, Kureimat will become the biggest electricity generation compound in Egypt with 2900 MW installed capacity, higher than the Aswan High Dam's 2100 MW.